Traffic Report

| October 29, 2015 | 0 Comments

November

3 / Tuesday

Cadet Sheridan — There will be a road closure on Cadet Sheridan Road for utility installation from 8:30 a.m. to 3:30 p.m., Nov. 3 to 10. Cadet Sheridan Road will be completely closed from the north side of Elou Street to the south side of Trimble Road.

A portion of the Trimble right-turn lane onto southbound Cadet Sheridan Road will also be closed.

Saturday and Sunday work will only be done if absolutely necessary, between 9 a.m. to 5 p.m. The contractor will have appropriate signs and barriers for this road closure.

Ongoing

Traffic Report

Traffic Report

Wilson Road — There will be intermittent road closures at Wilson Road in the vicinity of Bldg. 420, the Post Office and the intersection at Montgomery Drive, Fort Shafter, through Nov. 6, for the installation of a new water main line.

Intermittent road closures will follow from Nov. 9 to Dec. 20, from 7 a.m. to 5:30 p.m., excluding holidays.

During construction, traffic on Warner Road headed towards the PX will be detoured onto Pierce Street between Bldgs. 435 and 438. Traffic from the PX headed toward Warner Road will be detoured onto Montgomery Drive. Traffic on Montgomery Drive headed towards the PX parking lot will not be affected.

Long Construction — A partial, modified traffic flow and road closure near Schofield’s Nehelani for utility installation continues. The area near the loading docks and the parking lot between Bldgs. 2060, 2070 and 2071 are restricted though Dec. 28.

The work will be performed in phases. Parking is limited during closure.

 Leilehua Closure — Schofield’s Leilehua Avenue will be closed in phases in order to reconstruct the road.

  • Curb repair will take place until Nov. 18.
  • Phase 1 of Leilehua between Macomb and Kline/Gordon Lane will be Nov. 19-25.
  • Phase 2 between Kline/Gordon Lane and Stoneman Field Road will be Nov. 30 to Dec. 4. There will be no access to the parking of Bldg. 645, Family and Child Care and Garrison Sports Office.
  • Phase 3 between McCornack and the Stoneman Field Road will be Dec. 7-11.
  • Phase 1 through 3 closures will be 24 hours a day, seven days a week. The lanes between Leilehua and Waianae Ave that fall within the closed portions of Leilehua will be made two-way for residents only. On these lanes, there will be no parking in the Leilehua bound side of the road and no parking within 100 feet from Leilehua Avenue. The 100 feet no parking area will be used for cars to turn around.
  • Top lift paving and striping will be performed 8 a.m.-4:30 p.m., Dec. 14-17.

The contractor will have appropriate safety signs and barriers when the parking lot closes.