Traffic Report: February 26, 2016

| February 26, 2016 | 0 Comments

Traffic Report

Today

Thot-less — There’s a single lane closure, weekdays, 9 p.m.-5 a.m., on Kamehameha Highway at the Karsten Thot Bridge, between Kilani Avenue and Whitmore Avenue, for repairing and repainting of the bridge. This schedule will continue until Friday morning, March 11.

The closed lane will alternate between the northbound and southbound directions depending on the location of the work. During the closure hours, traffic will be contraflowed through the remaining open lane.

Karsten Thot Bridge

Karsten Thot Bridge

The height clearance for the bridge has been reduced from 14 feet 4 inches to 12 feet. Motorists are advised to plan ahead and drive with caution through the work zone. Roadwork is weather permitting.

 UPDATE, 10:52 a.m.
The Hawaii Department of Transportation (HDOT) successfully completed its planned night work requiring a single lane closure on Kamehameha Highway across the Karsten Thot Bridge in Wahiawa. The overnight closures referenced in the news release above that were scheduled to continue until Mar. 11 are no longer necessary. Crews will continue to make progress on the Repair and Repaint Karsten Thot Bridge project during daytime construction hours that do not require lane closures. Should overnight lane closures be needed in the future we will be sure to notify the public in advance.

HDOT thanks the public for its patience as we make the necessary repairs to extend the longevity of the bridge. For more information, please visit the project website at www.rrkarstenthot.com or call the project hotline at (808) 518-4576.

Hawaii-State-SealDepartment of Transportation Weekend Closures

Feb. 26-28

Lane closure schedules may change at any time without further notice.
All projects are weather permitting.

— H-1 FREEWAY —

1) HONOLULU (WEEKEND/NIGHT WORK)
Closure of the 5TH Avenue On-Ramp to the H-1 Freeway in the westbound direction on Sunday night, February. 28, from 11 p.m. to 4 a.m., nightly, for pole repairs

2) PEARL CITY TO WAIPAHU (WEEKEND/NIGHT WORK)
Right lane closures on the H-1 Freeway in the westbound direction between the Pearl City/Waimalu Off-Ramp (Exit 10) and the Waipahu Off-Ramp (Exit 8B) on Sunday night, Feb. 28, through Friday morning, Mar. 4, from 8 p.m. to 4:30 a.m., nightly, for bridge deck overlay work.

·        Two lanes closed from 8 p.m. to 8:45 p.m.
·        Three lanes closed from 8:45 p.m. to 4:30 a.m.

For more information, visit the project website at www.pmcontraflow.com or call the project hotline at (808) 945-1144.

3) WAIPAHU (WEEKEND/NIGHT WORK)
Up to three lanes closed on the H-1 Freeway in both directions between the Kamehameha Highway Overpass and the Waiawa Road Overpass on Sunday night, Feb. 28, through Friday morning, Mar. 4, from 8 p.m. to 4 a.m., nightly, for the rail project.

The number of lanes closed will vary depending on the location of the roadwork.

For more information, please visit the project website for The Rail at http://www.honolulutransit.org/.

4) WAIPAHU (WEEKEND/NIGHT WORK)
Closure of the Waipahu Off-Ramp (Exit 8B) from the H-1 Freeway in the westbound direction on Sunday night, Feb. 28, through Friday morning, Mar. 4, from 9 p.m. to 4 a.m., nightly, for the rail project.

— H-201 MOANALUA FREEWAY —

1) HALAWA (WEEKEND WORK)
Closure of the H-201 Moanalua Freeway in the westbound direction between the Puuloa Road/Tripler Hospital Off-Ramp (Exit 3) and the Kahuapaani Street Overpass on Saturday, Feb. 27, from 5 a.m. to 12:30 p.m., for medial repairs.

— FARRINGTON HIGHWAY —

1) EWA BEACH (WEEKEND/NIGHT WORK)
Closure of the Farrington Highway westbound off-ramp to the southbound Fort Weaver Road on Sunday night, Feb. 28, through Friday morning, Mar. 4, from 9 p.m. to 4 a.m., nightly, for the rail project.

2) NANAKULI (WEEKEND/NIGHT WORK)
Two lanes closed on Farrington Highway in the eastbound direction between Haleakala Avenue and Nanakuli Avenue on Sunday night, Feb. 28, through Friday morning, Mar. 4, from 9 p.m. to 4 a.m., nightly, for sewer installations. One lane will be open in each direction.

3) PEARL CITY (WEEKEND/NIGHT WORK)
Closure of the Farrington Highway eastbound off-ramp to the northbound H-2 Freeway on Sunday night, Feb. 28, through Friday morning, Mar. 4, from 9 p.m. to 4 a.m., nightly, for the rail project.

4) PEARL CITY (WEEKEND/NIGHT WORK)
Lane closures on Farrington Highway in westbound direction between Waiawa Road and the Kamehameha Highway Overpass on Sunday night, Feb. 28, through Friday morning, Mar. 4, from 9 p.m. to 4 a.m., nightly, for the rail project.

5) WAIPAHU (WEEKEND/NIGHT WORK)
Closure of the Farrington Highway eastbound off-ramp to the H-1 Freeway on Sunday night, Feb. 28, through Friday morning, Mar. 4, from 9 p.m. to 4 a.m., nightly, for the rail project.

— KAMEHAMEHA HIGHWAY —

1) KANEOHE (WEEKEND/NIGHT WORK)
Left lane closure on Kamehameha Highway in both directions between Luluku Road and Likelike Highway on Friday night, Feb. 26, through Saturday morning, Feb. 27, from 9 p.m. to 5 a.m. for pavement marking work.

— NIMITZ HIGHWAY —

1) KALIHI (WEEKEND WORK)
Right lane closure on Nimitz Highway in the westbound direction between Waiakamilo Road and Puuhale Road on Saturday, Feb. 27, from 6 a.m. to 2:30 p.m., for electrical work.

— MIDDLE STREET —

1) KALIHI (WEEKEND/NIGHT WORK)
Alternating lane closure on Middle Street in both directions between North King Street and Kamehameha Highway on Friday night, Feb. 26, through Saturday morning, Feb. 27, and Monday night, Feb. 29, through Saturday morning, Mar. 5, from 7 p.m. to 4 a.m., nightly, for the Middle Street Pavement Reconstruction project.

There will also be a 24/7 southbound median lane closure and sidewalk closure on the west side of Middle Street. Signage will be posted instructing pedestrians to use the east sidewalk.

— FORT WEAVER ROAD —

1) EWA BEACH (WEEKEND/NIGHT WORK)
Closure of Fort Weaver Road southbound off-ramp to the eastbound Farrington Highway on Sunday night, Feb. 28, through Friday morning, Mar. 4, from 9 p.m. to 4 a.m., nightly, for the rail project.

29 / Monday

Sterling and Airdrome — An adjusted schedule for traffic flow crossing Wheeler’s Airdrome Road at the intersection of Sterling Road is scheduled to end today. The project’s completion was delayed due to weather conditions and unexpected construction issues. Airdrome is converted from a two-way road to a one-lane contraflow around the construction area, weekdays, 8 a.m.-5 p.m.

 

April

Power Outage Graphic

2 / Saturday

Power Outage — As part of Schofield’s Quad B renovation project, a power outage is scheduled, 7 a.m.-3 p.m., that affects Area A housing 49-85.

 

4 / Monday

Williston Detour — A road closure on Schofield’s Williston Avenue between Cadet Sheridan Road to Reilly Avenue is scheduled to conclude today. Meanwhile, parking lots on Williston are still accessible.

Traffic is being detoured around the construction area through Cadet Sheridan, Menoher Road and Reilly Avenue.

 

30 / Saturday

Lauhala Closures — The road closure along Wheeler’s Lauhala Road in the housing area is scheduled to end today. The completion date of this traffic control plan was impacted by weather and was extended.

 

Ongoing

 

Kubo Closure — Intermittent road closures at Fort Shafter’s Kubo Street, weekdays, 7 a.m.-5:30 p.m., continue until May 13. This construction work will occupy Kubo from Bldg. T-126 to the intersection of Kubo and Funston Road at Bldg. 12.

Kubo Street and the adjacent parking lot will be restricted to contractor equipment for the duration of work in Area X.

Palm Circle Drive and Richardson Street will be accessible to the public by means of Hyland Lane.

 

Revised Lyman/Flagler — There are traffic modifications, weekdays, 7 a.m.-4 p.m., at Schofield’s intersection of Lyman and Flagler to widen Lyman Road, add a dedicated left turn lane, and add traffic and pedestrian signals to the intersection, until Aug. 12.

Construction will be phased, so road widening will be performed first, providing an additional lane. The majority of the project will allow traffic to flow in both directions of Lyman and Flagler. Turns will be limited at the intersection to provide two lanes of traffic.

 

Airdrome Road — One-lane road closures along Wheeler’s Airdrome Road from the sewage treatment plant to the flight simulator continue to June 30, weekdays, 8 a.m.-3:30 p.m., for the installation of new water and sanitary sewer lines.

The extension of this traffic control plan is due to unforeseen conditions with existing water lines.

 

Tags: , , , ,