Traffic & Outages

| May 22, 2018 | 0 Comments
Traffic & Outages

Traffic & Outages

November 2018

Health Clinic

Health Clinic

5 / Monday

Health Clinic Parking Lot, Schofield Barracks — There is a closure to a portion of the health clinic driveway for demolition, curb & gutter, underground electrical, light poles, asphalt paving, and striping work. Closure location is in the “right turn only” portion of the health clinic driveway just before the porte-cochere after entering from McCornack Road. The underground and new light pole electrical work will continue past the driveway closure location into the adjacent grassy area and not affect vehicular traffic. Work Dates are through Nov. 16. Closure will be 24 hours per day, seven days per week.

During this closure, access to the health clinic from the new parking lot is limited to foot traffic. Any vehicle needing to access the porte-cochere or handicap stalls just past the porte-cochere will need to enter through the old parking lot from Waianae Avenue. Exit from the porte-cochere will remain open.

Chanute Road, Schofield Barracks — Alutiiq will be conducting concrete pours for the new curbs, gutters, and sidewalks near Bldg. 107. The time frame will be through Jan. 31, 2019. The concrete pours will be scheduled from 8 a.m. to 3 p.m., Monday to Saturday. Alutiiq is requiring a partial road closure on Chanute Road near Bldg. 107. The reason for the partial road closure is to allow heavy equipment into and out of our job site for the new elevator shaft for Bldg. 107. We will be requiring to close one-lane on Chanute Road in order to safely position the concrete pump truck and concrete truck. The contractor will have appropriate signs and barriers for closing each side of the road way, and work zone flaggers will be positioned to assist traffic through the work zone area.

Alutiiq will also be requiring to close the parallel parking in front of Bldg. 107 for the concrete pours in order to safely position the concrete trucks. The work consists of two Phases. Phase 2 will be poured first, thus parallel parking in that phase will be closed. When completed with Phase 2, Phase 1 will be poured and at that time, parallel parking in that phase will
be closed. The contractor will have appropriate signs and barriers in place to direct pedestrians of the sidewalk closures. Work zone flaggers will be positioned to assist traffic through the work zone area.

Alutiiq will also be requiring a partial closure of the parking stalls between Bldg. 107 and 108 to proceed with project activities, and to maneuver heavy equipment into and out of the construction site safely without causing any damage to property, vehicles, or pedestrians. The contractor will have in place water barriers, delineators and crowd barriers to cordon off the “No Parking” stalls area with signs. All other parking stalls will be available for use.

Brannon Road

Brannon Road

Brannon Road, Schofield Barracks — There will be a partial closure of Brannon Road between Unnamed Street and Glennan Road for underground utility work. The lane will be closed intermittently between Nov. 5 and Jan. 3, 2019. Large vehicles entering Unnamed Street from Brannon Road will need to enter
from the McCornack direction. A detour will be in place for vehicles entering from the Glennan Road end. Closure hours will be between 7:30 a.m. and 4:30 p.m. Drivers will be required to follow the direction of the traffic control flagmen who will direct traffic during these hours.

26 / Monday

Takata Field — There will be a parking lot closure at Takata Field in order to replace lights. The closure will be Nov. 26 through May 31, 2019.  The parking lot closure will be in effect 24 hours a day, seven days a week. Please note that the project schedule is subject to change pending weather delays. The contractor will have appropriate safety signs and barriers when they close the Takata Field Parking Lot.

December

15 / Saturday

Fort DeRussy

Fort DeRussy

Fort DeRussy Outage — A power outage has been scheduled in the Fort DeRussy area on Saturday, Dec. 15, from 8 a.m. to 2 p.m. to perform electrical upgrades. The outage impacts Fort DeRussy, the DKI Asian Pacific Security Center, the parking garage, chapel and U.S. Army Museum. Note, times and locations are an estimate as field conditions may prompt additional time.

Ongoing

Kauhini Road, Aliamanu Military Reservation — Construction crews will be replacing the roof on a portion of Bldg. 1782 (AMR School Age). During this installation, Kauhini Road, directly in front of the School Age Center/Parent Central and to the front of the entrance of the AMR Community Center, will be blocked off. Ten stalls fronting Bldg. 1782 along Kauhini Road will also be temporarily unavailable to allow access to Maintenance for building materials. The closure will be in effect through Nov. 16, 24 hours a day.

The AMR Community Center Parking Lot will be opened during construction. The drive through area between the AMR Child Development Center and the AMR
School Age Center will remain open, only for brief drop offs. Please note that the project schedule is subject to change pending weather delays. The contractor will have appropriate safety signs and barriers when they close the roadway.

Brannon Road — There will be a partial closure of Brannon Road within the Medical Campus adjacent to the Schofield Barracks Federal Credit Union. The inbound lane will be closed intermittently through Nov. 22. All vehicles will still have access to the Medical Campus but will be required to follow the direction of flagmen. Closure hours will be between 7:30 a.m. and 4:30 p.m.

Lyman — There will be alternating lane closures at the Lyman/Humphrey’s intersection on Schofield Barracks. A left turn lane from Lyman to Humphreys will be installed. Closures will be from 8 a.m. to 4:30 p.m. The lane closures will be in effect through Jan. 31, 2009, on Monday through Friday. Please note that the project schedule is subject to change pending weather delays. The contractor will have appropriate safety signs and barriers when they close the roadway.

Fort Shafter Road Closures — Fort Shafter will have the following road closures in September through November:
* Phase 1: Hensel Phelps will be closing Bennet Drive from Montgomery Road to Pierce Road for installation of a new electrical duct bank through Nov. 2.
*
Phase 2: Bennet Drive will be closed from Pierce Road to Warner Road for the installation of a new electrical duct bank through Nov. 23.
Please note that the project schedule is subject to change pending weather delays. The contractors will have appropriate safety signs and barriers when they close the roadway.

Trimble Road — Partial road closures will occur on Trimble Road, Schofield Barracks, between the intersections of Carpenter Street and Hewitt Street. There will also be a lane closure on Trimble Road at Cadet Sheridan.  The road will be rehabilitated and concrete will be installed at the intersection medians. The closures will be from 8:30 a.m. to 4 p.m. and be in effect through Dec. 31Note, the project schedule is subject to change pending weather delays. The contractors will have appropriate safety signs and barriers when they close the roadway.

Area X — Road closures will occur from 7:30 a.m. to 4 p.m. for various streets at Area X in order to repave the roads. The road closures will be in effect through Oct. 31.

Tags: , ,

Category: Calendar, Traffic Report

Leave a Reply

Your email address will not be published. Required fields are marked *